A report that shows total wages by day of the week?

General support regarding TimeTrex, such as
configuring policies/taxes or processing payroll.
Locked
cmcgrath
Posts: 16
Joined: Mon Jan 07, 2013 1:49 pm

A report that shows total wages by day of the week?

Post by cmcgrath »

Is there a report I can run that breaks down total wages by day of the week?
shaunw
Posts: 7839
Joined: Tue Sep 19, 2006 2:22 pm

Re: A report that shows total wages by day of the week?

Post by shaunw »

In the new interface, yes.

However when you say "Day of week" are you referring to "Mon, Tue, Wed, ..." over multiple week period, or are you just wanting wages split out for each day of whatever period is defined?

Example 1 (Time Period: two weeks) :
-----------------------------
Week 1:
Mon: 16hrs
Tue: 16hrs
Wed: 16hrs
...
Week 2:
Mon: 16hrs
Tue: 16hrs
Wed: 16hrs
...

Example 2 (Time Period: two weeks):
-----------------------------
Mon: 32hrs
Tue: 32hrs
Wed: 32hrs
cmcgrath
Posts: 16
Joined: Mon Jan 07, 2013 1:49 pm

Re: A report that shows total wages by day of the week?

Post by cmcgrath »

Like example two.

I ran a report of my sales - year to date - by day of the week in my accounting software.

I would like to run a report in timetrex that shows labor by day of the week - year to date.

Thanks!
shaunw
Posts: 7839
Joined: Tue Sep 19, 2006 2:22 pm

Re: A report that shows total wages by day of the week?

Post by shaunw »

If you go to Report -> TimeSheet Reports -> TimeSheet Detail, then in the Template dropdown, select the last template called "All Time+Wage By Employee/Day Of Week". This template is split up by employee, if you don't want that simply remove the "Full Name" column from the Display Columns, Group By, Sub-Total By, and Sort dropdown boxes.
cmcgrath
Posts: 16
Joined: Mon Jan 07, 2013 1:49 pm

Re: A report that shows total wages by day of the week?

Post by cmcgrath »

Thank you!