Warning: Critical Maintenance Jobs have not run in the last 48hours

General support regarding TimeTrex, such as
configuring policies/taxes or processing payroll.
Post Reply
MickG01
Posts: 144
Joined: Mon Nov 09, 2009 11:48 am

Warning: Critical Maintenance Jobs have not run in the last 48hours

Post by MickG01 »

I have TimeTrex installed on and Ubuntu Server (non Gui) and this week got this error.

How do I address this? Thanks
mikeb
Posts: 709
Joined: Thu Jul 27, 2006 11:58 am

Re: Warning: Critical Maintenance Jobs have not run in the last 48hours

Post by mikeb »

Is this a new install or an existing installation that recently stopped working?
TimeTrex Community Edition is developed and supported by volunteers.
Help motivate us to continue by showing your appreciation!
MickG01
Posts: 144
Joined: Mon Nov 09, 2009 11:48 am

Re: Warning: Critical Maintenance Jobs have not run in the last 48hours

Post by MickG01 »

Been running for over a year.
It still is working it just got that annoying red header line this week
MickG01
Posts: 144
Joined: Mon Nov 09, 2009 11:48 am

Re: Warning: Critical Maintenance Jobs have not run in the last 48hours

Post by MickG01 »

OK I'll post this for others to see if they have this experience.
After the previous week's payroll run I was traveling and the pay Stubs and Pay period for that week were left open until I returned, found those messages, closed them, and entered a new week's payroll.
This morning I closed the most recent ones and the messages cleared away.
I find the message wording to be uninformative considering the manual marking of Pay Stubs as 'Paid' and the manual marking of a Pay Period as 'Closed' was the fix. Unless there's a task I should run or and automatic task should be set up to deal with these chores. However all is good now. Thanks for your time.
mikeb
Posts: 709
Joined: Thu Jul 27, 2006 11:58 am

Re: Warning: Critical Maintenance Jobs have not run in the last 48hours

Post by mikeb »

If the error message you received was in fact: "Warning: Critical Maintenance Jobs have not run in the last 48hours", then it has nothing to do with marking pay stubs as paid or closing pay periods. My guess is that whatever the problem was that was the causing the original message resolved itself some other way.
TimeTrex Community Edition is developed and supported by volunteers.
Help motivate us to continue by showing your appreciation!
MickG01
Posts: 144
Joined: Mon Nov 09, 2009 11:48 am

Re: Warning: Critical Maintenance Jobs have not run in the last 48hours

Post by MickG01 »

You are correct. The next time I started a new connection to the server, it returned.
So How do I track what it is complaining about?
mikeb
Posts: 709
Joined: Thu Jul 27, 2006 11:58 am

Re: Warning: Critical Maintenance Jobs have not run in the last 48hours

Post by mikeb »

You would need to enable logging as per the following FAQ, then next time the issue happens there would be detailed information in the log file if its related to TimeTrex that is.