Page 1 of 1

Accumulated Time total value showing more than expected

Posted: Wed Jun 29, 2016 12:06 am
by joshsard
Hi,

I have a question on the shown value of Accumulated Time in the TimeSheet. I created a pair of Punches (in/out) then the Accumulated Time shows our 'normal' daily total time which is '9:00' but when I delete the punch out and add again, the '9:00' suddenly becomes '18:00'. What could be the reason for this and the solution?

I am using Community Edition v9.0.2

Thanks
J

Re: Accumulated Time total value showing more than expected

Posted: Wed Jun 29, 2016 8:22 am
by shaunw
Please upgrade to the latest version of TimeTrex and if the problem persists attach a screenshot showing the full timesheet of the employee in question.